Project Name Location:  High Heavens Green Hub 

Description of Works:    Highway specification brushed finished concrete slabs and retaining walls
 
Client/Contractor:           J Browne Construction
 
Duration: 6 Weeks
 
Value:   £200,000
 
 ----------------------------------------------------------------------------------------------
 
Project Name Location:   Lea Valley Water Tanks
 
Description of Works:     Concrete Water Tanks
 
Client/Contractor:            Thames Valley Water/J Browne Construction
 
Duration: 3 Weeks
 
Value:   £27,000
 
----------------------------------------------------------------------------------------------
 
 Project Name Location:  Private Residence Hampstead
 
Description of Works:      Underpinning/drainage/ground floor slab and retaining wall
 
Client/Contractor:             RBS
 
Duration: 5 Weeks
 
Value:  £40,000
 
----------------------------------------------------------------------------------------------

Project Name / Location   Abingdon Road, High Street Ken, London W8

Description of Works        9 metre deep excavation plus RC frame 3 levels below ground and 4 above

Client / Contractor            Rackham Construction Limited

Duration: 32 weeks

Value:   £525,000

----------------------------------------------------------------------------------------------

Project Name / Location   Chiswick House Cafe, Chiswick, London

Description of Works        White Concrete Frame / Labour, Plant and Materials

Client / Contractor             English Heritage / Thomas Sinden

Duration: 10 weeks

Value:   £340,000

----------------------------------------------------------------------------------------------

Project Name / Location   Paynes Park Residential Development, Hitchin

Description of Works       Insitu concrete to 4000sq/m basement area with intricate steps, ramps, angled soffits retaining walls and radius columns

Client / Contractor            Stephen Howard Homes / Heritage Construction

Duration:  24 weeks

Value:   £500,000

----------------------------------------------------------------------------------------------

Project Name / Location    Grove Road Residential Development, Hitchin

Description of Works         Insitu concrete to 2700sq/m basement area with intricate steps, ramps, angled soffits retaining walls and radius columns

Client / Contractor              Stephen Howard Homes / Heritage Construction    

Duration: 13 weeks             (concrete work 3 wks ahead of schedule)

Value:   £240,000

----------------------------------------------------------------------------------------------

Project Name / Location     North Middlesex University Hospital Trust, Edmonton, London

Description of Works          RC Concrete for energy plant room & loading bays. Included compactor slabs & eco channels.

Client / Contractor              NHS Trust / J Browne Construction Ltd

Duration: 16 weeks

Value:   £125,000

----------------------------------------------------------------------------------------------

Project Name / Location     Stowe School, Buckingham

Description of Works         RC Frame, 5 levels including lift shaft & insitu stairs to create 3600m2 gross internal area. First fix and second fix carpentry.

Client / Contractor             Stowe School / WilliamSapcote & Sons Ltd

 Duration: 52 weeks           (concrete work 6 wks ahead of schedule)

Value:   £500,000

----------------------------------------------------------------------------------------------

Project Name / Location   Royal Hospital, Belfast

Description of Works       Ground Floor Slabs, Shuttering & Placing concrete

Client / Contractor            NHS / H. Devlin Contracts

Duration: 4 weeks

Value:   £25,000

----------------------------------------------------------------------------------------------

Project Name / Location     HSS Docks, Belfast

Description of Works        Construction of Weigh Bridges

Client / Contractor             Hss Docks / O.B. Construction

Duration: 4 weeks

Value:   £20,000

----------------------------------------------------------------------------------------------

Project Name / Location   Three Valleys Water, Hatfield

Description of Works         Construction of underground Water Tank

Client / Contractor             Three Valleys Water / J Browne Construction

Duration: 3 weeks

Value:   £19,000